This is a follow on information update for the upcoming project.
LARPD has approved the 100% design drawings for the Robertson Park resurfacing project. The plan includes artificial turf on both lighted fields with permanent soccer (yellow) and football (white) striping, and markers for laying out temporary lines for girls and boys lacrosse.
New drinking water facilities will be available at each team area on each field for ease of getting water. New electrical will be run throughout the area underneath and around the turf playing surface in preparation for future scoreboards, and for events that may require power. Football goal posts will be installed in sleeves so they can be removed or rotated to not interfere with soccer play.
LARPD’s tentative
schedule is to go out to bid in March/April, with bid openings and construction
starting in May/June. The current schedule is to finish everything in
December, however Fusion SC will work diligently with LARPD to make sure that the fields will
be open for play for our Fall season, even if some of the miscellaneous finish work may
lag till the end of the year.
This will be a state of the art, modern sports facility that will greatly benefit our children into the future. Fusion SC is very proud to be an integral part of bringing this dream to reality for Livermore.